Storage Objective Function Module
=================================
EELT7030 — Operation and Expansion Planning of Electric Power Systems
Federal University of Paraná (UFPR)
Author
------
Augusto Mathias Adams <augusto.adams@ufpr.br>
Summary
-------
This module defines the **objective function** for the energy storage subsystem,
used in the Mixed-Integer Linear Programming (MILP) formulation of the
operation and expansion planning problem.
Description
-----------
The objective function represents the **total system cost** associated
with the operation and investment of storage units.
It aggregates two main cost components:
1. **Operational Cost (c_op)** — proportional to the total amount of energy moved
(charging and discharging), weighted by the duration of each load level.
2. **Investment Cost (c_inv)** — proportional to the existence of installed
capacity throughout the planning horizon.
Both cost components are expressed as additive terms in a global minimization
objective, consistent with standard formulations in expansion planning models.
Mathematical Formulation
------------------------
The objective function is defined as:
\[
\min \; Z =
\sum_{s \in SU} \sum_{t \in T} \sum_{p \in P}
h_p \, c^{op}_s \, (P^{ch}_{s,t,p} + P^{dis}_{s,t,p})
+ \sum_{s \in SU} \sum_{t \in T}
c^{inv}_s \, x_{s,t}
\]
where:
| Symbol | Description |
|:--------|:------------|
| \(h_p\) | Duration of load level \(p\) (hours) |
| \(c^{op}_s\) | Operational cost of unit \(s\) (per MWh) |
| \(c^{inv}_s\) | Investment cost of unit \(s\) |
| \(P^{ch}_{s,t,p}\) | Charging power (MW) |
| \(P^{dis}_{s,t,p}\) | Discharging power (MW) |
| \(x_{s,t}\) | Binary existence variable |
| \(SU, T, P\) | Sets of storage units, time steps, and load levels |
Functions
---------
set_objective_storage(m)
Adds the objective function to the Pyomo model, minimizing total storage costs.
Notes
-----
- The function assumes that all sets, parameters, and variables
have already been defined (typically via `storage_add_sets_and_params`
and `storage_add_variables`).
- Units are consistent with the rest of the framework:
MW for power, MWh for energy, and monetary units for costs.
- The resulting objective is fully compatible with mixed-integer solvers
such as CBC, GLPK, or commercial solvers (Gurobi, CPLEX).
References
----------
[1] CEPEL. *DESSEM — Manual de Metodologia*, 2023.
[2] Unsihuay Vila, C. *Introdução aos Sistemas de Energia Elétrica*, Lecture Notes, UFPR, 2023.
"""
from pyomo.environ import ConcreteModel, Objective, minimize
[docs]
def set_objective_storage(m: ConcreteModel) -> ConcreteModel:
"""
Define the total cost minimization objective for the storage subsystem.
This function constructs a Pyomo `Objective` expression that
aggregates operational and investment costs for all storage units
across time steps and load levels.
Parameters
----------
m : pyomo.environ.ConcreteModel
Pyomo model instance containing all sets, parameters, and variables
related to the storage subsystem.
Returns
-------
pyomo.environ.ConcreteModel
The same model instance, now with an attached objective function
named `OBJ`.
Examples
--------
>>> from pyomo.environ import ConcreteModel
>>> m = ConcreteModel()
>>> # (Assume sets and parameters already defined)
>>> set_objective_storage(m)
>>> print(m.OBJ.sense)
minimize
"""
def _obj_rule(m):
expr = sum(
# Operational cost: proportional to charging and discharging energy
m.level_hours[p] * m.storage_c_op[s] * (
m.storage_ch[s, t, p] + m.storage_dis[s, t, p]
)
for s in m.SU for t in m.T for p in m.P
) + sum(
# Investment cost: proportional to installed capacity
m.storage_c_inv[s] * m.storage_x[s, t]
for s in m.SU for t in m.T
)
return expr
# Define objective: minimize total storage cost
m.OBJ = Objective(rule=_obj_rule, sense=minimize)
return m